The 24 hours Daily Cycle
Concrete cube test completed by Engineer. Striking of Tunnel forms can begin



1st Half Tunnelform is removed Cleaned, oiled and repositioned
Wall reinforcement placed in advance Services are placed within the walls



Final packages are lifted into position Conduits are placed for services within the slab – reinforcement completed Once 2 half tunnels are placed then reinforcement can be placed on deck



Concrete pouring can start Walls followed by slabs (2 to 3 hours) Vibrators are used to ensure a high quality finish



Curtains are closed and space heaters inserted Heating system can be used to accelerate the curing process,
The exercise is repeated the following day…